Hallandale Beach Minutes
133
Total Documents
Apr 2026 — May 2026
Date Range
Recent Documents
ORDINANCE REGULATING ELECTRIC SCOOTERS AND ELECTRIC SCOOTERS AND MICROMOBILITY DEVICES — Exhibit 1 - Ordinance — City Commission (2026-05-20)
The City of Hallandale Beach is creating new rules for electric scooters and similar devices. Riders can use them on city streets but not on sidewalks or in parks...
View original →Additional Design Services for the EV Bus Facility (M2303) — Agenda Cover Memo — City Commission (2026-05-06)
The City Commission considered approval of Change Order #4 to the contract with Saltz Michelson Architects for Phase 2 building construction documents for the EV Bus Charging and Maintenance Facility at the Public Works Compound. The change order totals $280,781...
View original →CAMERAS REPLACEMENT PROJECT. — Exhibit 1 - Golden Isles Camera Replacement Project — GISND Board of Directors (2026-05-06)
UNDERGROUND UTILITY — Golden Isles Undergrounding & Other Capital Improvement Projects Funding Strategy Presentation — GISND Board of Directors (2026-05-06)
The City of Hallandale Beach held a workshop on May 6, 2026, to discuss funding strategies for the Golden Isles Safe Neighborhood District (GISND) $7. 87M–$39...
View original →CITY BUDGET DISCUSSION. — Exhibit 3 - Bus Bench Shelter Presentation — City Commission (2026-05-06)
CITY BUDGET DISCUSSION. — Exhibit 2 - Chaves Lake Presentation — City Commission (2026-05-06)
The City of Hallandale Beach presented a consolidated financial and project strategy for the Chaves Lake Projects, a portfolio of four interdependent capital projects totaling $24. 6 million in identified appropriations...
View original →CITY BUDGET DISCUSSION. — Exhibit 1 - Budget Presentation — City Commission (2026-05-06)
School Zone Camera Speed Detection Program Ordinance — Exhibit 4 - School Zone Camera Speed Enforcement Program Presentation — City Commission (2026-05-06)
The Hallandale Beach Police Department received a presentation on the School Zone Camera Speed Enforcement Program, authorized under Florida State Statute 316. 1906 (HB657/588)...
View original →ORDINANCE REGULATING ELECTRIC SCOOTERS AND ELECTRIC SCOOTERS AND MICROMOBILITY DEVICES — Exhibit 2 - Ordinance Options for Motorized Personal Transportation Presentation — City Commission (2026-05-06)
The Hallandale Beach Police Department issued an April 2026 report identifying the need for municipal regulation of e-scooters, motorized bicycles, and similar non-human powered devices. The city currently has no specific codes governing these devices...
View original →Additional Design Services for the EV Bus Facility (M2303) — Exhibit 1 - Resolution — City Commission (2026-05-06)
The City Commission authorized a fourth change order to Saltz Michelson Architects, Inc. for an additional $300,256...
View original →Additional Design Services for the EV Bus Facility (M2303) — Exhibit 13 - Resolution No. 2026-010 — City Commission (2026-05-06)
The City of Hallandale Beach Commission authorized Change Order No. 3 to the Department of Public Works Electric Vehicle Bus Charging and Fleet Facilities design contract with Saltz Michelson Architects, Inc...
View original →Additional Design Services for the EV Bus Facility (M2303) — Exhibit 12 - Consultant's Fee Proposal — City Commission (2026-05-06)
This is a professional services proposal from Saltz Michelson Architects for additional architectural and engineering services on the City's EV Bus Charging Stations project at 630 NW 2nd Street. The firm requests approval and payment of $79,495...
View original →Additional Design Services for the EV Bus Facility (M2303) — Exhibit 14 - Phase 2 Design Fee Proposal — City Commission (2026-05-06)
Sal Michelson Architects requests authorization from the City of Hallandale Beach for additional professional services totaling $300,256. 60 for redesigning the EV Bus charging station maintenance building...
View original →Additional Design Services for the EV Bus Facility (M2303) — Exhibit 11 - Terracon Phase 2 Limited Site Investigation Report - Terracon - 8-6-25 — City Commission (2026-05-06)
Terracon Consultants submitted a Limited Site Investigation report on August 6, 2025, for a proposed Electric Bus Charging and EV Facility at 650 NW 2nd Street, Hallandale Beach. The report details soil and groundwater testing conducted July 15, 2025, including five soil borings and temporary monitoring wells...
View original →Additional Design Services for the EV Bus Facility (M2303) — Exhibit 10 - Terracon Phase I Environmental Site Assessment - 6-28-23 — City Commission (2026-05-06)
Terracon Consultants completed an environmental assessment of a proposed Electric Bus Charging & Fleet Facility in Hallandale Beach. The study reviewed the site and four nearby properties (a debris staging area, design company, warehouse, and water treatment plant) for environmental hazards...
View original →Additional Design Services for the EV Bus Facility (M2303) — Exhibit 9 - Resolution No. 2023-163 — City Commission (2026-05-06)
The Hallandale Beach City Commission unanimously approved Resolution 2023-163 on December 20, 2023, authorizing a second design change order for the Department of Public Works Electric Vehicle Bus Charging and Fleet Facilities project. The change order increases the contract with Saltz Michelson Architects, Inc...
View original →Additional Design Services for the EV Bus Facility (M2303) — Exhibit 8 – Resolution No. 2023-143 — City Commission (2026-05-06)
The City of Hallandale Beach Commission approved Resolution 2023-143, authorizing a major development review and zoning variance for a 5,077-square-foot administration and maintenance building with EV bus charging bays at the Public Works Compound. The Planning and Zoning Board had recommended approval on September 27, 2023...
View original →Additional Design Services for the EV Bus Facility (M2303) — Exhibit 7 – Concept No. 1 Design Fee Proposal — City Commission (2026-05-06)
Saltz Michelson Architects submitted a proposal dated November 6, 2023, for Phase II design services of the EV Bus Charging Stations Maintenance Building Redesign at 630 NW 2nd Street, Hallandale Beach. The total design fee is $970,782...
View original →Additional Design Services for the EV Bus Facility (M2303) — Exhibit 6 – Resolution No. 2023-056 — City Commission (2026-05-06)
The City of Hallandale Beach Commission authorized a change order of $25,565 for additional design work on the EV Bus Charging and Fleet Facilities project, plus a 10% contingency of $72,532. Saltz Michelson Architects, Inc...
View original →Additional Design Services for the EV Bus Facility (M2303) — Exhibit 5 – SW Corner Design Fee Proposal — City Commission (2026-05-06)
SMA proposes additional design and construction administration services for the City of Hallandale Beach's EV Bus Charging and Fleet Facilities project at the Public Works Complex (630 NW 2nd Street). The scope covers approximately 5,600 square feet of site design, including demolition of existing vehicle wash equipment and design of electrical infrastructure for EV bus charger transformers, meters, and switchgear...
View original →Sign up free to browse all 133 minutes
Create Free AccountGet notified when new minutes are filed in Hallandale Beach
Instant alerts starting at $4.99/mo